Thar power projects to be completed ahead of schedule

News Image

MG News | June 14, 2017 at 01:44 PM GMT+05:00

0:00

Karachi : Thar coal mining and 660MW power project in Thar Block II will be completed ahead of the scheduled time, the commissioning date is set at 3rd June 2019, said the Sindh Engro Coal Mining Company (SECMC) Chief, Shamsuddin Ahmed Shaikh on Wednesday.

“Despite declaring Gorano reservoir project technically and environmentally sound by the judicial committee of Sindh High Court, we are ready to talk with the protesters to remove their concerns which were created by misinformation”, he was addressing to an Iftar Dinner ceremony held in Mithi the other evening.
Sharing the details of the coal mining project, Mr. Shaikh said that the company has achieved 40 percent of mining and 33 percent progress on the power projects in 15 months after the financial closure achieved in April 2016.

“The total duration envisaged for completion of the project was set at 42 months, but the pace of the work ensures us of its completion in 38 months instead,” he added.
He asserted that he strongly believes that benefits from the coal projects in Thar should go to the locals of Thar before the rest of the country and, that's why, he added, the company has started interventions in education, health, livelihood, and drinking water sectors for the people of the area – and the schemes have already started benefiting the locales.

Member of Sindh Assembly from district Tharparkar, Dr. Mahesh Malani said that Thar Coal Block II project is one of the largest of the energy schemes of Pakistan and it is a blessing for the people of Thar.

Dr. Malani assured that Sindh Government through its elected representatives is ready to guarantee that no damage would occur to the locales living around the Gorrano Reservoir. He also said that the government was considering a package for the Gorrano community which would be announced soon.

Addressing the question pertaining to the technicalities of the Gorrano reservoir, he said that the feasibility study has been prepared by the reputable international firms and it is in no one's favour to challenge their reports which have been carefully drafted after comprehensive research considering all aspects.

He said that contrary to the misconception spread by certain elements, the project shall benefit the Thar and Tharis on a large scale which would surely change the face of the area from being a poverty-stricken to a prosperous region.

Related News

Name Price/Vol %Chg/NChg
KSE100 155,384.51
274.67M
0.61%
944.82
ALLSHR 95,133.57
856.28M
0.49%
465.41
KSE30 47,466.99
137.10M
0.74%
347.09
KMI30 227,645.22
99.71M
0.67%
1519.50
KMIALLSHR 63,888.06
353.11M
0.50%
319.01
BKTi 41,761.78
72.20M
0.33%
138.95
OGTi 31,619.14
7.57M
0.41%
130.35
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 115,260.00 117,240.00
114,940.00
-2005.00
-1.71%
BRENT CRUDE 67.19 67.52
66.78
0.20
0.30%
RICHARDS BAY COAL MONTHLY 84.00 0.00
0.00
-1.20
-1.41%
ROTTERDAM COAL MONTHLY 93.00 0.00
0.00
0.05
0.05%
USD RBD PALM OLEIN 1,106.50 1,106.50
1,106.50
0.00
0.00%
CRUDE OIL - WTI 62.97 63.24
62.52
0.28
0.45%
SUGAR #11 WORLD 15.96 15.98
15.80
0.17
1.08%

Chart of the Day


Latest News
September 15, 2025 at 05:30 PM GMT+05:00

KAPCO reports significant profit decline in FY25


September 15, 2025 at 04:19 PM GMT+05:00

PSX Closing Bell: A Bullish Beat Goes On


September 15, 2025 at 04:10 PM GMT+05:00

PKR strengthens 3 paisa against USD



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg