NTDC fined Rs. 10 million for delaying in projects

News Image

MG News | February 15, 2018 at 04:48 PM GMT+05:00

National Electric Power Regulatory Authority (NEPRA) has imposed fine of Rs. 10 million on M/s National Transmission and Despatch Company Limited (NTDC) on account of un-due delay in power evacuation projects including transmission lines for power plants and development works.

The Authority has taken serious note of abnormal delay in completion of interconnection arrangement for 404 MW Uch-II power plant (i.e. 220 kV Uch-II to Sibi, Transmission Line, 125 km), said a press release issued here Thursday.

Uch-II is one the cheapest gas based power plant which is currently operating on interim arrangement. The plant was commissioned in April 2014 and it has been underutilized due to incomplete interconnection arrangement.

Similar is the case of 747 MW Guddu new power plant, which was commissioned in April 2014 and is still operating on interim arrangement despite lapse of almost four years.

Furthermore, as per contract 220 kV Mansehra, 220 kV Chakdara, 220 kV D.I Khan and 220 kV Nowshera grid stations were required to be completed by December 2016. However, the said grid stations are still not completed; consequently certain areas of

KPK which include Mansehra, Hazara, Swat, D.I Khan are facing low voltage and power supply constraints.

500-kV Rahim Yar Khan grid station is delayed by 6 years, 220 kV Dera Murad Jamali grid station is delayed by 4 years and 220 kV Ghazi Rd Lahore grid station is also delayed by more than 1 year.

The work is ongoing on these grid stations. Moreover, 220 kV Chistian and 220 kV Gujrat grid stations have been completed with a delay of 3 years and 2 years respectively.

The delay in projects has not only caused serious technical and financial complications but also resulted in low voltages and extended hours of load shedding.

NTDC being a National Grid Company within the meaning of Section 18 of the NEPRA Act, is responsible to operate and provide safe, reliable transmission and interconnection services to power plants.

Moreover, Authority vide its instruction dated 11.09.2015 inter alia directed NTDC to expedite work on all delayed projects and ensure their completion as per contractual completion dates. However, NTDC failed to full fill its obligation under NEPRA Act and also failed to comply with directions of the Authority – APP

Related News

Name Price/Vol %Chg/NChg
KSE100 167,193.44
366.12M
0.88%
1456.68
ALLSHR 101,164.95
815.04M
0.80%
806.11
KSE30 49,320.68
134.37M
0.99%
482.30
KMI30 238,958.16
110.19M
0.84%
2000.56
KMIALLSHR 65,336.06
481.98M
0.82%
528.42
BKTi 46,284.55
24.74M
0.99%
454.81
OGTi 33,773.06
6.87M
0.71%
237.97
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 79,950.00 81,340.00
79,565.00
-1575.00
-1.93%
BRENT CRUDE 114.50 114.94
113.25
-0.82
-0.71%
RICHARDS BAY COAL MONTHLY 128.50 0.00
0.00
0.25
0.19%
ROTTERDAM COAL MONTHLY 145.70 145.70
145.60
-0.15
-0.10%
USD RBD PALM OLEIN 1,182.50 1,182.50
1,182.50
0.00
0.00%
CRUDE OIL - WTI 101.94 102.31
100.56
-0.84
-0.82%
SUGAR #11 WORLD 19.68 19.80
19.34
0.34
1.76%

Chart of the Day


Latest News
October 29, 2026 at 04:56 PM GMT+05:00

KIBOR climbs as SBP raises policy rate to 12%


October 29, 2026 at 04:43 PM GMT+05:00

KPT facilitates 51,000 tons of wheat handling


October 29, 2026 at 04:38 PM GMT+05:00

Gold price in Pakistan remain unchanged


October 29, 2026 at 04:31 PM GMT+05:00

Pakgen Power’s 9MCY26 loss widens to Rs325m


October 29, 2026 at 04:18 PM GMT+05:00

D.G. Khan cement profit rises 24% to Rs3bn in 1QFY27



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg