FCL reports smooth expansion progress, targets October completion
MG News | March 04, 2026 at 10:50 AM GMT+05:00
March 04, 2026 (MLN): Fast Cables Limited (PSX: FCL) has provided an update on the progress of its expansion project, more than a year after its successful debut on the Pakistan Stock Exchange, saying the majority of committed milestones have been completed while the remainder are on track to be wrapped up by October 2025.
The company raised Rs 3,129,600,000 through its Initial
Public Offering in June 2024, issuing 128 million ordinary shares at a strike
price of Rs24.45 per share with a face value of Rs 10 each.
The IPO placed 20.35% of the company's post-IPO share
capital in the hands of public and institutional investors, and shares were
officially listed and began trading on the PSX on June 10, 2024.
The funds raised were earmarked for a defined set of
expansion activities, the implementation of which the company has been required
to report on as per the prospectus commitments outlined in Note 4.6.
Several key phases of the project have been completed
without issue. The installation of plant and machinery that was already
delivered was finalised by Q2 FY2023.
Civil works at the company's existing Unit-II facility were
completed by Q3 FY2024, as were the mechanical and electrical upgrades at the
same facility.
Loan repayments tied to plant, machinery, and building
construction at Unit-II were also fully settled by Q4 FY2024.
The one area where progress has lagged is land acquisition.
Originally targeted for completion by Q4 FY2024, only 30% of the land earmarked
for the current expansion has been acquired so far.
The remaining land intended for future phases of expansion
is still being sourced.
The company said the delay is a result of a deliberate
approach, noting that it has been carefully evaluating available parcels on the
basis of location suitability, competitive pricing, and land availability,
rather than acquiring at any price.
On the land that has been secured, building construction is
complete and operational.
As of June 30, 2025, the company reported that 71% of the
new machinery had been delivered to the plant site, with the remaining units
received after the financial year ended.
Of what has been delivered, approximately 20% is fully
installed and operational.
The rest is currently undergoing installation, testing, and
commissioning activities, which the company expects to complete by October
2025.
Both trial production and full commercial production
originally targeted for Q4 FY2025 are contingent on the completion of these
final steps.
The company has said it expects those targets to be met once
the October commissioning deadline is achieved.
Fast Cables added that despite the slight adjustment to the original timeline, the overall project is progressing well and remains on course for a successful conclusion.
The aforementioned information was disseminated through a notification to Exchange.
Copyright Mettis Link News
Related News
| Name | Price/Vol | %Chg/NChg |
|---|---|---|
| KSE100 | 155,467.41 282.83M | -1.06% -1664.69 |
| ALLSHR | 92,822.49 432.80M | -0.80% -744.37 |
| KSE30 | 47,782.54 96.31M | -1.08% -520.44 |
| KMI30 | 219,402.33 84.27M | -0.63% -1396.18 |
| KMIALLSHR | 59,773.02 197.06M | -0.36% -215.50 |
| BKTi | 45,459.94 27.75M | -1.59% -733.14 |
| OGTi | 30,438.74 22.32M | 0.81% 245.64 |
| Symbol | Bid/Ask | High/Low |
|---|
| Name | Last | High/Low | Chg/%Chg |
|---|---|---|---|
| BITCOIN FUTURES | 68,820.00 | 69,160.00 67,615.00 | 355.00 0.52% |
| BRENT CRUDE | 83.61 | 83.73 81.28 | 2.21 2.72% |
| RICHARDS BAY COAL MONTHLY | 99.40 | 0.00 0.00 | -7.85 -7.32% |
| ROTTERDAM COAL MONTHLY | 124.15 | 139.50 124.15 | 5.35 4.50% |
| USD RBD PALM OLEIN | 1,083.50 | 1,083.50 1,083.50 | 0.00 0.00% |
| CRUDE OIL - WTI | 76.39 | 76.51 74.37 | 1.83 2.45% |
| SUGAR #11 WORLD | 13.95 | 14.20 13.91 | 0.04 0.29% |
Chart of the Day
Latest News
Top 5 things to watch in this week
Pakistan Stock Movers
| Name | Last | Chg/%Chg |
|---|
| Name | Last | Chg/%Chg |
|---|
Trade Balance