Rs 46,302.528 million released for NHA projects under PSDP

News Image

By MG News | January 01, 2020 at 04:56 PM GMT+05:00

0:00

January 01, 2020: The government has released Rs 46,302.528 million for under-construction projects of National Highway Authority (NHA) under Public Sector Development Programme (PSDP) in the current fiscal year out of the total allocation of Rs154966.835 million till end of December 2019.

An official source on Wednesday informed APP that for construction of Hakla-D I Khan Motorway, the total allocation of Rs 11500 million was made which has already been released. For four-lane bridge across Indus River linking Layyah with Taunsa including 2-lane approach road and river training works having 24 km length, a total of Rs 1000 million have been allocated out of which Rs 500 million have been released, he informed.

He further said for construction of 18.3 km six-lane highway from Kala Shah Kaku to Lahore Ring Road including over Ravi River (Lahore Eastern Bypass) a total of Rs 1090.589 have been earmarked which have already issues.

The official said for land acquisition, affected Properties Compensation and Relocation of Utilities for Construction of 6-Lane Highway from Kala Shah Kaku to Lahore Ring Road (18.3 KM) including bridge over Ravi River (Lahore Eastern Bypass) Rs 1250 million have been allocated out of which Rs 650 million have been released.

He said out of Rs 1500 million set aside for land acquisition, affected properties compensation and relocation of utilities for construction of Burhan/Hakla to D.I. Khan Motorway Rs 750 million have been issued so far.

He said Rs 1931.980 million have been earmarked for construction of 29.1 km Burhan-Havelian Expressway (E-35) out of which Rs 810 million have been issued whereas out of Rs 5000 million allocated for Construction of Faisalabad-Khanewal (M-4), 184-km Rs 500 million have been released. Out of Rs 4000 million allocated for Sarai Gambila-Kohat section of Indus Highway, Rs 1600 million have been issued.

For dualization and Improvement of Pindigheb- Kohat Road Rs 2000 million have been earmarked out of which Rs 1000 million have been issued so far, he said adding that for improvement and widening of additional two-lanes on either side of Thokar Niaz Baig to Hudyiara Drain Multan Road N-5, Rs1000 million had been allocated which has already been released.

The official said for improvement, up-gradation and widening of Jaglot-Skardu Road (S-1,167 km) Rs 3500 million have been allocated out of which Rs1750 million have been issued, he said adding that for Lahore-Multan Motorway (M-3 section) of Karachi - Lahore Motorway, Rs 4500 million have been allocated out of which Rs2340 million have been released so far.

APP

Related News

Name Price/Vol %Chg/NChg
KSE100 126,754.27
50.68M
0.90%
1126.95
ALLSHR 79,130.95
161.20M
0.70%
546.23
KSE30 38,487.02
7.41M
0.87%
333.23
KMI30 185,943.25
17.36M
0.57%
1056.75
KMIALLSHR 54,042.30
81.20M
0.52%
278.49
BKTi 32,346.29
16.07M
1.33%
424.61
OGTi 27,745.16
0.62M
-0.10%
-28.83
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 107,635.00 108,105.00
107,505.00
-600.00
-0.55%
BRENT CRUDE 66.44 66.63
66.34
-0.30
-0.45%
RICHARDS BAY COAL MONTHLY 97.00 97.00
97.00
1.05
1.09%
ROTTERDAM COAL MONTHLY 107.65 107.65
105.85
1.25
1.17%
USD RBD PALM OLEIN 998.50 998.50
998.50
0.00
0.00%
CRUDE OIL - WTI 64.78 65.02
64.67
-0.33
-0.51%
SUGAR #11 WORLD 16.19 16.74
16.14
-0.52
-3.11%

Chart of the Day


Latest News
July 01, 2025 at 09:56 AM GMT+05:00

PSX Opening Bell: Off to a Flying Start


July 01, 2025 at 09:30 AM GMT+05:00

Asia markets mixed amid tariff uncertainty


July 01, 2025 at 06:00 AM GMT+05:00

MG Morning Breeze: Updates to Skim before Market



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg