Sazgar Engineering discloses progress of its 'Four Wheeler Project'

News Image

MG News | February 21, 2019 at 03:19 PM GMT+05:00

February 21, 2019 (MLN): Sazgar Engineering Works Limited has disclosed progress regarding the Four Wheeler Project via a notification to the PSX issued on Thursday.

According to the notice, the construction and civil work is near to completion, whereas procurement of plant and machinery, hiring of marketing and technical staff is in progress. During the period, the company also imported samples of some vehicles for display purposes.

However, due to un-avoidable circumstances, the Board has revised the estimated date of completion of project from June 30, 2019 to December 31, 2019.

Copyright Mettis Link News

Related News

Name Price/Vol %Chg/NChg
KSE100 176,975.76
93.47M
0.01%
9.07
ALLSHR 107,530.96
236.46M
-0.06%
-68.80
KSE30 52,644.11
31.40M
-0.00%
-0.42
KMI30 251,330.69
41.09M
-0.07%
-185.13
KMIALLSHR 69,409.42
166.19M
-0.17%
-116.62
BKTi 49,803.50
3.53M
0.08%
41.30
OGTi 36,637.99
3.89M
-0.52%
-193.31
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 80,840.00 81,350.00
78,710.00
1990.00
2.52%
BRENT CRUDE 91.20 92.90
91.18
-0.97
-1.05%
RICHARDS BAY COAL MONTHLY 110.30 0.00
0.00
-0.20
-0.18%
ROTTERDAM COAL MONTHLY 124.55 124.55
124.55
0.00
0.00%
USD RBD PALM OLEIN 1,228.00 1,228.00
1,228.00
0.00
0.00%
CRUDE OIL - WTI 84.17 85.84
84.14
-0.84
-0.99%
SUGAR #11 WORLD 17.66 17.69
17.08
0.05
0.28%

Chart of the Day


Latest News
August 25, 2026 at 11:18 AM GMT+05:00

PM Shehbaz launches National Olive Value Chain Policy


August 25, 2026 at 10:51 AM GMT+05:00

Govt vows smooth DAP supply, FMD-free zone along motorway


August 25, 2026 at 10:47 AM GMT+05:00

Bitcoin climbs above $80,000 after $4bn short squeeze


August 25, 2026 at 10:29 AM GMT+05:00

Govt retires Rs326bn debt in a week



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg