Mettis Global News
Mettis Global News
Mettis Global News
Mettis Global News

MPS Preview: High for Longer

Neelum Jhelum Project’s 1st Unit successfully completes reliability test – Commercial operation to be started soon

Share on facebook
Share on twitter
Share on linkedin
Share on whatsapp

The first unit of Neelum Jhelum Hydropower Project successfully completed the reliability test today, paving the way for its commercial operation.  Under the protocols, the unit will now be checked completely and adjustments if any will be carried out by the manufacturer / contractor.

The unit is expected to start commercial operation thereafter. The first generating unit of Neelum Jhelum Hydropower Project was synchronized with the system on April 9. The second unit was scheduled in May, however, WAPDA succeeded in commissioning this unit for trial generation ahead of schedule and synchronized it with the National Grid on April 22. Both generating units, have provided around 20 million units of electricity to the National Grid during their test run.

The 969 MW-Neelum Jhelum Hydropower Project has four generating units, each of them having generation capacity of 242.25 MW. The remaining units are likely to commence by end June 2018 operation at one month interval each.

Neelum Jhelum Hydropower Project, constructed on River Neelum in Azad Jammu and Kashmir, is considered to be an engineering wonder, 90 percent of which exists underground in high mountainous region.

The project has three main components including a 60 feet high and 160 feet long composite dam, a 52-kilometer long water way system and an underground power house. Besides, a 525 KV switch yard and transmission line have also been constructed to evacuate electricity, generated by the project. Neelum Jhelum Hydropower Project will contribute about 5 billion units of electricity to the National Grid annually.

The total revenue generation is expected to be over Rs 55 Billion annually.

Posted on: 2018-05-04T16:47:00+05:00