BFAGRO reports IPO proceeds utilization progress

News Image

MG News | May 21, 2026 at 02:52 PM GMT+05:00

May 21, 2026 (MLN): Barkat Frisian Agro Limited (PSX:BFAGRO) has reached full mechanical completion of its egg processing facility, with all plant and machinery installations successfully finished and production was scheduled to commence in April 2026.

The milestone, reported in the company's Quarterly Progress Report for the period ended March 31, 2026, reflects on-schedule progress in the utilization of IPO proceeds in line with the objectives outlined in the Prospectus.

All core egg processing equipment has been installed and commissioned, along with essential utility systems including refrigeration machinery, chillers, heaters, and air compressors. The project has now entered its final phase of testing, commissioning, and operational optimization.

On the civil works front, land development and construction have been substantially completed, with only finishing activities remaining in ancillary facilities and supporting structures, expected to wrap up in the coming quarter.

Similarly, mechanical, electrical, and plumbing works are largely finalized, including HT/LT systems, transformers, cabling, lighting, firefighting, CCTV, networking, and security systems.

On the infrastructure side, advance payment for the solar power system has been made with installation progressing on schedule, while procurement of furniture and fittings is nearing completion. All major statutory approvals, NOCs, permits, and certifications have been secured.

Regarding working capital, the company's unutilized IPO proceeds remain retained and are proposed to be deployed toward working capital requirements in the next quarter, consistent with the offer document.

The status of IPO Funds utilization as of March 31, 2026 is as follows:

S. No.

Purpose

Allocation Costs (Rs.)

Funds utilized (Rs.)

Percentage of utilization

1

Plant and machinery

470,395,564

(484,523,110)

103%

2

Civil work and land development charges

212,646,072

(207,625,832)

97.64%

3

Mechanical and electrical installation

75,000,000

(49,538,984)

66.05%

4

project supports and infrastructure costs

122,513,364

(71,621,551)

58.46%

Grant Total

880,555,000

(813,309,477)

92.36%

The aforementioned information was disseminated through a notification to Exchange.

Copyright Mettis Link News

Related News

Name Price/Vol %Chg/NChg
KSE100 168,405.69
233.50M
2.17%
3574.27
ALLSHR 101,440.68
611.82M
2.12%
2106.96
KSE30 50,536.03
111.32M
2.39%
1179.20
KMI30 242,252.33
92.93M
2.12%
5040.15
KMIALLSHR 65,990.87
334.25M
1.89%
1223.46
BKTi 46,146.24
41.80M
2.61%
1173.23
OGTi 35,657.04
9.04M
2.37%
825.71
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 77,845.00 78,275.00
77,190.00
140.00
0.18%
BRENT CRUDE 104.07 106.80
103.68
-0.95
-0.90%
RICHARDS BAY COAL MONTHLY 110.00 0.00
0.00
-8.75
-7.37%
ROTTERDAM COAL MONTHLY 113.00 0.00
0.00
0.50
0.44%
USD RBD PALM OLEIN 1,191.50 1,191.50
1,191.50
0.00
0.00%
CRUDE OIL - WTI 97.56 100.11
97.25
-0.70
-0.71%
SUGAR #11 WORLD 14.84 15.01
14.83
0.11
0.75%

Chart of the Day


Latest News
May 21, 2026 at 02:55 PM GMT+05:00

TGL secures land for new value-added glass plant


May 21, 2026 at 02:52 PM GMT+05:00

BFAGRO reports IPO proceeds utilization progress


May 21, 2026 at 02:15 PM GMT+05:00

Gold price in Pakistan rises Rs5,000 per tola



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg