Neelum Jhelum Hydropower Project fast heading towards completion

News Image

MG News | July 28, 2017 at 04:47 PM GMT+05:00

First unit to start generation by February 2018

The strategically important Neelum Jhelum Hydropower Project (NJHP) is fast heading towards its completion, and is scheduled to start electricity generation with commissioning of its first generating unit by February 2018.

NJHP Board of Management (BoM) briefed WAPDA Chairman Lt Gen Muzammil Hussain (R) during a meeting. BoM Chairman Mr. Peter Mason and the members including Mr. Rusten, Mr. Chirst, Project Manager Mr. Geoff attended the meeting. WAPDA Member (Power) Badr-ul-Munir Murtiza, Advisor (Projects) Nasir Hanif, NJHP CEO Brig (R) Muhammad Zareen, NJHP Project Director and others were also present in the meeting.

Speaking on the occasion, WAPDA Chairman expressed satisfaction over the progress on the project, adding that despite the delay of years and cost overrun, the project will finally see the light of the day because of some extraordinary commitment and display of professional excellence by WAPDA and NJHP team members. He directed the project management that the pace of work be continued with the same zeal to complete the project in accordance with the timelines.

Earlier, the meeting was briefed that filling of water in NJHP reservoir will start in October, water way system (tunnels diverting water from dam to power house) is scheduled to be completed by end December 2017, pressurizing the water way system will start in January 2018, while wet testing / commissioning of the power generating units to commence in February 2018.

It is worth mentioning that Neelum Jhelum Hydropower Project comprises of four generating units with cumulative generation capacity of 969 MW. The first unit will start electricity generation by February 2018, the second unit in mid March, whereas the third and the fourth units will be completed in April 2018. On its completion, the project will contribute about five billion units of electricity to the National Grid every year. Annual revenue of the project is estimated to be Rs.45 billion.

Related News

Name Price/Vol %Chg/NChg
KSE100 177,663.90
235.58M
-0.22%
-396.79
ALLSHR 106,405.65
716.40M
-0.33%
-354.52
KSE30 51,898.87
70.89M
-0.24%
-126.47
KMI30 256,704.92
82.01M
-0.34%
-885.94
KMIALLSHR 68,872.28
248.22M
-0.34%
-233.39
BKTi 48,359.55
20.14M
-0.23%
-109.54
OGTi 35,584.86
2.92M
-0.33%
-118.63
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 59,100.00 60,290.00
58,110.00
-785.00
-1.31%
BRENT CRUDE 90.79 93.17
89.86
-0.88
-0.96%
RICHARDS BAY COAL MONTHLY 126.00 126.00
126.00
0.00
0.00%
ROTTERDAM COAL MONTHLY 136.25 136.25
136.25
-0.55
-0.40%
USD RBD PALM OLEIN 1,047.50 1,047.50
1,047.50
0.00
0.00%
CRUDE OIL - WTI 83.33 86.60
82.57
-0.35
-0.42%
SUGAR #11 WORLD 18.81 19.10
18.68
0.47
2.56%

Chart of the Day


Latest News
November 29, 2026 at 03:44 PM GMT+05:00

PIA sets sights on 50-aircraft order in 2027


November 28, 2026 at 10:26 PM GMT+05:00

ECC raises wheat import ceiling to 2.5m tonnes for FY27


November 28, 2026 at 01:55 PM GMT+05:00

Key Pakistan Market Stats and Economic Indicators



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg