Mohmand Dam to be ready before 2024 flood season

News Image

MG News | July 15, 2019 at 09:40 AM GMT+05:00

July 15, 2019: The multi-purpose Mohmand dam will be ready before the flood season of 2024 as work is in full swing.

Official sources told APP that as per PC-1, the estimated cost of the dam is two hundred and ninety-one billion rupees and it would take around five years to complete.

They said Water and Power Development Authority would provide sixty-seven per cent fund for the project while remaining thirty-seven per cent would be provided by the government.

On completion, the project will store about 1.2 million-acre feet of water, generate eight hundred megawatts of low-cost hydel electricity and help mitigating floods in Peshawar, Charsadda and Naushera.

Related News

Name Price/Vol %Chg/NChg
KSE100 178,953.76
5.21M
0.39%
691.42
ALLSHR 108,258.19
23.05M
0.39%
420.75
KSE30 53,575.59
2.70M
0.43%
227.91
KMI30 252,642.26
3.26M
0.45%
1131.90
KMIALLSHR 69,478.13
7.93M
0.44%
304.27
BKTi 51,252.31
0.48M
0.37%
187.59
OGTi 35,457.26
0.19M
0.59%
208.84
Symbol Bid/Ask High/Low
Name Last High/Low Chg/%Chg
BITCOIN FUTURES 63,295.00 64,810.00
63,035.00
-1670.00
-2.57%
BRENT CRUDE 87.33 88.06
86.40
-1.03
-1.17%
RICHARDS BAY COAL MONTHLY 105.75 0.00
0.00
-1.55
-1.44%
ROTTERDAM COAL MONTHLY 120.00 120.00
120.00
-0.25
-0.21%
USD RBD PALM OLEIN 1,175.00 1,175.00
1,175.00
0.00
0.00%
CRUDE OIL - WTI 81.69 82.24
80.60
-0.92
-1.11%
SUGAR #11 WORLD 14.56 14.75
14.54
-0.21
-1.42%

Chart of the Day


Latest News
July 28, 2026 at 09:21 AM GMT+05:00

Oil falls below $88 on easing U.S. Iran tensions


July 28, 2026 at 09:11 AM GMT+05:00

NBP issues foreign exchange rates


July 28, 2026 at 07:58 AM GMT+05:00

MG Morning Breeze: Updates to Skim before Market



Top 5 things to watch in this week

Pakistan Stock Movers
Name Last Chg/%Chg
Name Last Chg/%Chg