Govt moves to dissolve P3A, merge functions into Privatization Commission
MG News | November 18, 2026 at 12:29 PM GMT+05:00
November 18, 2026 (MLN): A draft bill seeks to dissolve the Public Private Partnership Authority (P3A) and merge its functions into the Privatization Commission, which would be renamed the Privatization and Public Private Partnership Commission.
The change would take effect at once on commencement. The
bill amends the Privatization Commission Ordinance, 2000, and would repeal the
law that created the P3A. The P3A would be dissolved without any winding-up or
further formality
All of the P3A’s assets, rights, powers, property, cash and
bank balances, reserve funds, investments, debts, liabilities and obligations
would be transferred to the Commission.
The P3A’s budget provision and the balance in its fund would
move to the Commission Fund. Contracts, obligations and legal proceedings of
the P3A would be treated as those of the Commission. Any reference to the P3A
in a statutory instrument or document would be read as a reference to the
Commission.
P3A officers, consultants, advisers, auditors, employees and
other staff would be retained by the Commission for six months or until their
contracts expire, whichever is earlier, on terms no less favourable than
before.
After that period, the Commission could reassign them within
its structure or discontinue their engagement. Those discontinued would receive
the notice period or salary in lieu, along with all dues accrued up to that
date.
Rules, regulations, notifications and orders issued under
the P3A’s law would remain in force, to the extent they do not conflict with
the Ordinance, until repealed, altered or replaced.
Seven P3A instruments would be repealed outright: the
Working Party Rules, 2021, the P3WP Regulations, 2025, the Board Procedures
Regulations, 2024, the Financial Management Regulations, 2022, the Approvals
and Process Flow Regulations, 2021, the Human Resources Regulations, 2022, and
the Qualified Project Criteria Regulations, 2023.
Acts done, approvals granted and obligations incurred under
these instruments before commencement would stay valid.
The bill also adds public private partnership (PPP) to the
Ordinance’s title, preamble and the Commission’s name. The new preamble cites
the need for an enabling environment for private-sector participation in
development projects and public infrastructure.
It also cites a regulatory framework to mobilize private
investment and expertise, and to promote efficiency and transparency. The
Commission’s powers would be amended so that it can attract private-sector
investment where applicable.
The bill replaces the Ordinance’s definitions with a new set
covering PPPs. A PPP is defined as a commercial transaction between a
government agency and a private party in which the private party performs part
of the agency’s functions or develops a public asset or service.
It must also assume substantial financial, technical or
other project risks. Its return can come from payments by the government
agency, user charges and fees, revenues from approved commercial use of the
project, or a combination of these.
PPP project support from the federal government or any
public-sector entity may include licences and clearances, utility connections
for power, gas and water, land acquisition and rights of way, and
rehabilitation and resettlement of displaced persons. It may also include
environmental approvals, leasing or mortgage rights over public land and
infrastructure, viability gap funding and guarantees against political or other
risks.
The definitions also introduce new structures, including PPP
nodes within government agencies, a PPP transaction execution committee and a
risk management unit.
They also cover a PPP project development facility, a public
contribution fund, a viability gap fund and a category of “below threshold” PPP
projects.
Regulatory authorities named in the definitions include the
Pakistan Telecommunication Authority, the National Electric Power Regulatory
Authority and the Oil and Gas Regulatory Authority. For privatization,
transactions below a threshold set by the Commission, or those exempted by it,
would not be treated as privatization.
Copyright Mettis Link News
Related News
| Name | Price/Vol | %Chg/NChg |
|---|---|---|
| KSE100 | 176,817.55 104.94M | -0.39% -700.19 |
| ALLSHR | 106,156.27 470.62M | -0.29% -303.56 |
| KSE30 | 51,559.14 41.02M | -0.37% -193.92 |
| KMI30 | 253,442.28 45.44M | -0.37% -943.57 |
| KMIALLSHR | 68,674.12 184.10M | -0.37% -253.92 |
| BKTi | 48,635.87 13.81M | -0.37% -182.41 |
| OGTi | 35,784.50 2.15M | -0.51% -183.86 |
| Symbol | Bid/Ask | High/Low |
|---|
| Name | Last | High/Low | Chg/%Chg |
|---|---|---|---|
| BITCOIN FUTURES | 64,720.00 | 65,245.00 64,075.00 | 765.00 1.20% |
| BRENT CRUDE | 91.55 | 93.37 91.43 | -1.59 -1.71% |
| RICHARDS BAY COAL MONTHLY | 127.15 | 0.00 0.00 | 1.15 0.91% |
| ROTTERDAM COAL MONTHLY | 134.00 | 135.00 134.00 | -1.00 -0.74% |
| USD RBD PALM OLEIN | 1,182.50 | 1,182.50 1,182.50 | 0.00 0.00% |
| CRUDE OIL - WTI | 82.75 | 84.77 82.63 | -3.26 -3.79% |
| SUGAR #11 WORLD | 18.17 | 18.33 17.97 | 0.07 0.39% |
Chart of the Day
Latest News
Top 5 things to watch in this week
Pakistan Stock Movers
| Name | Last | Chg/%Chg |
|---|
| Name | Last | Chg/%Chg |
|---|
Nominal/Real Effective Exchange Rates Indices