WAPDA files an application of LPM to NEPRA

Share on facebook
Share on twitter
Share on linkedin
Share on whatsapp

May 28, 2019 (MLN): Pakistan Water and Power Development Authority (WAPDA) filed an application of License Proposed Modification (LPM) in the existing generation license of WAPDA Hydroelectric to NEPRA, in which revision in total generation capacity values of two Hydel Power Stations namely,  Golen Gol Hydropower Project from 106MW to 108 MW and Keyal Khwar Hydropower Project from 122 MV to 128MV was requested.

According to the NEPRA, as a result of the requested changes, the total installed capacity of WAPDA Hydroelectric shall increase from 17359.96 MW to 17367.96 MW.

Moreover, there would be no adverse impact on the tariff, quality of service and obligations of the WAPDA under the generation license.