May 29, 2019 (MLN): The 660MW Unit 2 coal-fired power plant of the China Power Hub Generation Company (Pvt.) Limited was successfully synchronized with the national grid of Pakistan on May 28, 2019 as per schedule. 

The synchronization, an important milestone towards the commercial operations of the Power Plant, comes exactly 5 months to the day when Unit 1 of the Project was synchronized, on December 28, 2018.

Both the Units of CPHGC are now providing electricity to the Pakistan national grid on pre-commissioning trial basis. Synchronization of Unit 2 was achieved within the agreed technical parameters laying the foundation for future commercial operations of the Project which is planned to start in August 2019.

Speaking at the occasion, Mr. Zhao Yonggang, CEO, China Power Hub Generation Company (Pvt.) Ltd. congratulated the CPHGC team, saying that, “China Power Hub Generation Company (Pvt.) Limited is a priority project under the China Pakistan Economic Corridor and is also the first overseas thermal power project developed by SPIC under the Belt & Road Initiative,” said Mr. Yonggang.

Located in Hub, Balochistan, the CPHGC Project is a Joint Venture Company between CPIH (the Chinese state-owned company) that owns 74% and HUBCO that owns 26%.

The Project despite the much higher cost, has adopted supercritical technology for environment protection. This technology requires reduced coal consumption and has lower carbon emissions thus improving its energy-conserving and environment protecting features.

The $2 billion Project includes a power plant and a dedicated coal Jetty. During commercial operations, the project will provide 9 billion kWh electricity to the national grid every year which will meet the electricity needs of 4 million households in Pakistan.

The CPHGC 2 x 660MW Coal-Fired Power Project officially had its ground breaking on March 21, 2017 and it is on track to be commercially operational in August 2019 that will help to alleviate a substantial part of electricity shortage in Pakistan and promote local social and economic development.

 

Posted on: 2019-05-29T12:41:00+05:00